What is required in terms of presence during a final inspection?

  1. The client must be there

  2. A witness is needed

  3. The contractor must be onsite

  4. No one is required to be present

The correct answer is: The contractor must be onsite

During a final inspection, it is essential for the contractor to be onsite. This requirement ensures that the contractor can address any questions or issues that may arise during the inspection process. The presence of the contractor allows for immediate clarification of any concerns that the inspector may have about the work completed, ensuring that all aspects of the project meet local codes and standards. Furthermore, having the contractor present can facilitate communication between the inspector and the contractor, which can lead to faster resolutions and a more efficient inspection process. This requirement also emphasizes the contractor's responsibility and accountability for the work performed. It provides an opportunity for the contractor to demonstrate their knowledge of the project details and to showcase the quality of their work to the inspector. Overall, the contractor’s presence during a final inspection is critical for ensuring compliance and for successfully concluding the project.