For buildings without basements, what is the required setback for septic tanks?

  1. 20 feet

  2. 10 feet

  3. 5 feet

  4. 15 feet

The correct answer is: 10 feet

The required setback for septic tanks in buildings without basements is 10 feet. This regulation is in place to ensure proper functioning of the septic system and to protect groundwater from contamination. A setback distance is crucial as it creates a buffer zone that helps minimize the risk of surface runoff or leaks affecting the areas where potable water or food sources are present. Understanding the regulations surrounding septic systems is vital for maintaining public health and environmental safety. While different states and local jurisdictions may have varying requirements, in Georgia, the minimum 10-foot distance is significant as it reflects both health concerns and practical aspects of installation and maintenance. This requirement ensures that septic systems operate effectively and reduces the likelihood of system failure or environmental impact.